For the population of Lerwick, on the Shetland Islands, the concept of incinerating waste to provide heat is critical, especially in winter where temperatures can fall below 0 °C.
Their existing process is centred on a Distributed Control System (DCS) which controls their entire operation, from regulating their 1100 OC furnace, to ensuring that pressure and temperature levels are correct for the water as it is pumped around Lerwick.
This DCS was approaching obsolescence, and hence needed to be replaced and upgraded to enhance performance and facilitate future proofing.
DAI, a Dematic company are known experts in the provision of DCS (distributed control systems) solutions, and have a proven track record in the delivery of business critical systems to the Energy sector. In addition DAI, a Dematic company are Siemens PCS7 partners, with a relationship going back over 30 years.
(Since the successful delivery of this project and others, an on-going continual improvement strategy by DAI, a Dematic company in Siemens technology has resulted in a joint DAI, a Dematic company and Siemens investment in a new state of the art demonstration facility at the Dematic Aberdeen offices manned by Dematic and Siemens experts. We are the only UK partner to offer this type of Siemens demo facility, which allows prospective customers to see how their solution might work for real.)
The wish for the new system was to have a stable solution, which was built around open technology, hence to offer Shetland Heat Energy and Power (SHEaP) greater choice and flexibility moving forward.
Since the system was critical for heat provision to Lerwick, any replacement needed to be fully up and running, and well tested, before the significant demands of the winter months arose.
The migration path adopted, from the old obsolescent DCS to the new DCS needed to have an easy to execute fall back plan to ensure the well being of the Lerwick population during the project execution.
Dematic engineered a new DCS solution based around Siemens PCS7, replacing the legacy ABB Advant DCS.
To help reduce project timescales and costs, existing I/O modules were retained.
Through the flexibility of the system, Dematic built several features into the changeover strategy to help keep the risk of operational disruption to a minimum.
In addition new functionality was introduced to make things work better and more efficiently than they had before.
Within 3 months of the migration, tangible benefits were obvious from the new system. Among other things, there were clear improvements in furnace regulation and consequently a reduction in maintenance time. Other benefits included a very operator friendly solution.
The DCS is used across the entire process, from regulating the temperature in the Energy Recovery Plant (ERP) that is annually incinerating more then 22,000 tonnes of waste, through to ensuring the temperature and pressure levels are correct as the water is pumped around Lerwick.
“We are very happy. There is no doubt that it works a lot more smoothly.” commented Neville Martin, District Heating Manager for SHEaP.
Aberdeen
3 Kingshill Park,
Venture Drive,
Westhill, Aberdeenshire,
AB32 6FL
United Kingdom
Basel
Clarastrasse 15,
Postfach
CH-4005
Basel
Switzerland
Manchester
Milan Court,
Bird Hall Lane,
Stockport,
SK3 0WZ
United Kingdom
Shanghai
Unit 2316, 5 Corporate Avenue,
150 Hubin Road,
Huangpu District,
Shanghai 200010
China